Sulphur 425 Jul-Aug 2026

13 July 2026
Restart for Hongda smelter
Hongda’s 100,000 t/a zinc smelter, in China’s Sichuan Province, completed scheduled maintenance and equipment upgrading and officially resumed production on 21st June, the company said. The smelter had been shut down for planned maintenance since January, during which time a modernisation project for the electrolytic zinc smelting system was also carried out. Following the nearly six-month revamp, the resumption of production is expected to improve overall operational efficiency, reduce unit production costs, and increase the utilisation rate, The company said. The stable supply of sulphuric acid generated by the zinc smelter will effectively leverage the synergies of the “sulphur-phosphorus” industrial chain in the company, an help alleviate cost pressures on the company’s phosphorus chemical business segment.