Skip to main content

Sulphur 410 Jan-Feb 2024

Case study: Replacement of upper part of a co-current flow quench tower


TOWER REVAMPING

Case study: Replacement of upper part of a co-current flow quench tower

This case study reports on the successful collaboration of two experienced partner companies to replace the problematic upper part of a co-current flow quench tower in a spent acid plant and shows the benefits of using resistant, pre-lined workshop fabricated equipment.

Eco Services’ Dominguez Plant operates a spend acid unit production facility in Long Beach, California. After the spent acid furnace and the waste heat boiler the acid gas with a temperature of 358°C has to be cleaned and cooled down to 80°C in a co-current flow quench tower (see below).

The original quench tower was built in 1989 for the predecessor company Stauffer.

Quench tower damage

Due to the high thermal, chemical and mechanical stress in the quench tower the acid resistant brick lining system had suffered from frequent damage during its 30 years of operation (see below, right).

The problem

Eco Services had to repair the acid resistant brick lining system at every turnaround. The costs for the repairs were very high and the duration of the shutdowns was often 2-3 weeks long. Eco Services used several different materials for the repair, including monolithic spray systems with anchors etc. several times but the materials were not resistant. Due to unforeseen damage in the upper part of the quench tower, Eco Services experienced lost production and high maintenance costs associated with this tower.

View of upper part of quench tower before replacement (above); damage to inside and outside of quench tower before replacement of upper part (right).

Finding a solution

Eco Services explained the issues with this acid resistant brick lining system to STEULER-KCH GmbH at the Sulphur + Sulphuric Acid Conference in Houston in 2020 and asked for a repair proposal.

After receiving the inquiry and reviewing the detailed technical information (steel and brick lining drawings, complete stress data, process description, loads of the piping etc.) STEULER-KCH GmbH recommended installing a new, acid and heat resistant brick lining system that would be installed in their workshop in Germany and then delivered together with the upper part of the steel apparatuses as a pre-lined workshop fabricated equipment ready for service on site to the Martinez Plant in LA.

Besides the detailed technical design for the lining system STEULER-KCH GmbH was also responsible for designing, building, and delivering the new, necessary upper steel part.

Pictures below show various manufacturing and installation stages involved of the project. During a shutdown the damaged existing upper part of the quench tower was removed and the new pre-brick lined equipment was installed. The works on site was carried out by Eco Services contractors under technical supervision of a STEULER-KCH GmbH rubber-and brick lining specialist.

1. Step: Steel fabrication

Grinding of welds to radius 5 mm

2. Step: Surface treatment

Sandblasting inside and outside grade Sa 2½ roughness 65 μm

3. Step: Rubber lining and outside painting

Rubber lining, Vulcoferran 2206 4 mm thickness single-ply soft rubber lining based on bromobutyl rubber (BIIR)

4. Step: Vulcanisation

Upper part after vulcanisation

5. Step: Brick lining

Installation of inner layer of special shaped graphite bricks with tongue and groove

6. Step: Transportation to site

Tranportation of the upper part to site

7. Step: Installation on site

Old upper part after lifting out New upper part before lifting in
Installation of rubber and brick lining in connection area after welding new part to existing quench tower

Main benefits

The main benefits of the pre-lined lining systems in this case were:

  • everything delivered from a single source;
  • execution of the highest level in the workshop;
  • no expensive weather protection and scaffolding on site;
  • lower travel and accommodation expenses;
  • no loss of time on site due to internal regulations;
  • no harmful influences (gas, steam, acid etc.) during work on site;
  • better and safer cost control;
  • no visa application and safety instruction on site for many fitters;
  • very limited time on site and extreme reduction of shutdown period;
  • working conditions/environment under defined conditions in the workshop;
  • no transport costs for materials and tools to site and back;
  • significantly lower cost for installation.

Latest in Equipment

New boilers enhance performance and reliability

A European ammonia plant, has successfully restarted following a revamp of the process gas cooling section, executed by Casale. Casale replaced the outdated boilers located downstream of the secondary reformer with three new double-tube type boilers supplied by Arvos. The new boilers were installed in the same location as the previous ones, minimising investment costs and plant modifications. The more robust and reliable design of the Casale-Arvos boilers has resulted in enhanced overall performance and reliability of the ammonia plant.

New contracts for Stamicarbon

Maire Group says that its nitrogen fertilizer technology licensor Stamicarbon has been awarded new contracts related to its NX STAMI UreaTM technology in Canada. The first award is a process design package and the licensing of an integrated urea and diesel exhaust fluid (DEF) production plant currently being developed by Genesis Fertilizers, a farmer-owned consortium, at Belle Plaine, Saskatchewan. The plant will have a urea melt capacity of 2,500 t/d, with operations expected to begin by 2029. Also thanks to a carbon capture and sequestration unit, it will be the first proposed low-carbon nitrogen fertilizer plant in Canada. Stamicarbon will apply its proprietary flash urea melt technology to enhance operational efficiency and reliability while minimising process steam consumption. The plant will also include a DEF facility with a production capacity of 1,500 t/d.