Skip to main content

Sulphur 420 Sep-Oct 2025

Lyten acquires Northvolt


Lyten acquires Northvolt

The Northvolt Ett battery factory in Skellefteå, Sweden

Lyten, a global leader in lithium-sulphur batteries has entered into a binding agreement to acquire Northvolt’s assets in Sweden and Germany. The acquisition includes Northvolt Ett and, Northvolt Labs in Sweden and Northvolt Drei in Germany. Additionally, Lyten is acquiring all remaining Northvolt intellectual property. The financial terms of the agreement were not disclosed. In total, Lyten’s acquisition includes assets valued at approximately $5 billion, including 16 GWh of existing battery manufacturing capacity, more than 15 GWh of capacity under construction, the infrastructure and plans to scale to more than 100 GWh, and the largest and most advanced battery R&D centre in Europe.

Lyten plans to rehire a significant portion of the previously laid-off workforce at these facilities and will assess staffing needs site by site. The company says that it sees substantial value in retaining local expertise and is committed to building long-term employment opportunities as we restart and scale operations.

“This is a defining moment for Lyten,” stated Dan Cook, Lyten CEO and Co-Founder. “Lyten’s mission is to be the leading supplier of clean, locally sourced and manufactured batteries and energy storage systems in both North America and Europe. The acquisition of Northvolt’s assets brings the facilities and Swedish talent to accelerate this mission by years, just at the moment when demand for Lyten lithium-sulphur batteries is growing exponentially to meet energy independence, national security, and AI data centre needs.”

The acquisition is being funded through equity investment into Lyten from private investors. Lyten expects the acquisitions to close in the fourth quarter of this year. The company says that it is also committed to pursuing the acquisition of Northvolt Six in Quebec, Canada, which is constructing a 15 GWh Phase 1 battery manufacturing facility. Lyten currently manufactures lithium-sulphur batteries in Silicon Valley and is selling commercially into the rapidly growing drone and defence markets.

Latest in Europe

Equinor backs out of blue hydrogen project

Norwegian oil and gas major Equinor says that it is no longer pursuing its planned H2M Eemshaven blue hydrogen project in the Netherlands, citing policy uncertainty and insufficient funding. The project was a joint venture between Equinor and Linde, and would have produced hydrogen from natural gas piped from Norway, with a capacity of 210,000 t/a of hydrogen beginning in 2029. Around 95% of the carbon dioxide produced would then be piped back to offshore storage sites near the Norwegian coast. Equinor had received a grant of €162 million for the project from the European Innovation Fund last summer. However, uncertainties over whether the project would receive carbon credits under the EU’s RED III directive, and a lack of local hydrogen infrastructure at Eemshaven meant that the project was unable to secure offtake agreements.

Avalon seeking permits for hydrogen plant

Avalon Renovables says that it has begun the administrative process to obtain environmental permits for the company’s planned Arquillo green hydrogen plant at Jerez de la Frontera. The plant is one of eight green hydrogen plans planned as part of the Bays of Algeciras and Cádiz Project (PBAC), with pipeline tie-ins to the future green ammonia plant in Campo de Gibraltar. The plant will include a 47 MW solar voltaic power plant called Arquillo, feeding 35 MW of electrolysis capacity, with an estimated output of 4,900 t/a of hydrogen.

Cancellation for green ammonia project

Hy2Gen has been forced to end plans for a green ammonia plant in Norway, following the withdrawal of an electricity supply agreement by the main energy provider. Iverson eFuels, co-owned by Hy2Gen and Copenhagen Infrastructure Partners, had been planning to build a 200,000 t/a green ammonia plant at Birkeland in Sauda, using 240 MW of electrolysis capacity. However, the plant’s operational schedule has been pushed back from an original launch date of 2027 to 2031, prompting Norwegian electrical grid operator Statnett to withdraw the 270 MW of previously allocated grid capacity at the end of December, saying that it could only offer the extra capacity once upgrades to the grid had been completed in the period 2033-35. Following several weeks of discussions, Iverson eFuels said in a statement that: “such an unresolved situation related to the completion of new network capacity is not compatible with further development of the project. On this basis, Iverson has decided to terminate the project concerning green ammonia production in Sauda. The company regrets the decision, thanks its partners, and will now consider the possibility of establishing a data centre to create new activity in Sauda.”