Skip to main content

Nitrogen+Syngas 396 Jul-Aug 2025

Koppö Energia to license thyssenkrupp Uhde methanol technology


Koppö Energia Oy has ordered a FEED (front end engineering design) contract from thyssenkrupp Uhde for its planned green methanol plant, as part of a power-to-x (P2X) project being developed by Koppö Energia in Kristinestad, Finland. The methanol plant will have a planned capacity of 450 t/d to support the maritime and e-gasoline fuel markets. Renewable hydrogen will come from a 200MW water electrolysis plant. CO2 will be captured in the city of Vaasa in Finland from a waste incineration facility. It will then be liquified and transported via trucks to the P2X facilities.

Nadja Håkansson, CEO of thyssenkrupp Uhde said of the award: “We are proud that our technology and implementation know-how will contribute to this pioneering project by Koppö Energia Oy. This is an excellent proof point for cross-industrial cooperation in the establishment of green methanol as a fuel.”

Thomas Zirngibl, Director at Koppö Energia said: “We are very pleased to cooperate with thyssenkrupp Uhde on this project as they bring the right technologies as well as the integration skills for ensuring a smooth tie-in and project delivery.”

Latest in Europe

Equinor backs out of blue hydrogen project

Norwegian oil and gas major Equinor says that it is no longer pursuing its planned H2M Eemshaven blue hydrogen project in the Netherlands, citing policy uncertainty and insufficient funding. The project was a joint venture between Equinor and Linde, and would have produced hydrogen from natural gas piped from Norway, with a capacity of 210,000 t/a of hydrogen beginning in 2029. Around 95% of the carbon dioxide produced would then be piped back to offshore storage sites near the Norwegian coast. Equinor had received a grant of €162 million for the project from the European Innovation Fund last summer. However, uncertainties over whether the project would receive carbon credits under the EU’s RED III directive, and a lack of local hydrogen infrastructure at Eemshaven meant that the project was unable to secure offtake agreements.

Avalon seeking permits for hydrogen plant

Avalon Renovables says that it has begun the administrative process to obtain environmental permits for the company’s planned Arquillo green hydrogen plant at Jerez de la Frontera. The plant is one of eight green hydrogen plans planned as part of the Bays of Algeciras and Cádiz Project (PBAC), with pipeline tie-ins to the future green ammonia plant in Campo de Gibraltar. The plant will include a 47 MW solar voltaic power plant called Arquillo, feeding 35 MW of electrolysis capacity, with an estimated output of 4,900 t/a of hydrogen.

Cancellation for green ammonia project

Hy2Gen has been forced to end plans for a green ammonia plant in Norway, following the withdrawal of an electricity supply agreement by the main energy provider. Iverson eFuels, co-owned by Hy2Gen and Copenhagen Infrastructure Partners, had been planning to build a 200,000 t/a green ammonia plant at Birkeland in Sauda, using 240 MW of electrolysis capacity. However, the plant’s operational schedule has been pushed back from an original launch date of 2027 to 2031, prompting Norwegian electrical grid operator Statnett to withdraw the 270 MW of previously allocated grid capacity at the end of December, saying that it could only offer the extra capacity once upgrades to the grid had been completed in the period 2033-35. Following several weeks of discussions, Iverson eFuels said in a statement that: “such an unresolved situation related to the completion of new network capacity is not compatible with further development of the project. On this basis, Iverson has decided to terminate the project concerning green ammonia production in Sauda. The company regrets the decision, thanks its partners, and will now consider the possibility of establishing a data centre to create new activity in Sauda.”